Project Schedule (Updated March 2022)
Activity | Date |
---|---|
Right-of-Way Acquisition - Middle Segment (Craft Road to Winchester Road) |
2019-2022 |
Right-of-Way Acquisition - South Segment (Shelby Drive to Craft Road) |
2022-2022 |
Construction - Middle Segment (Craft Road to Winchester Road) |
2023-2025 |
Construction - South Segment (Shelby Drive to Craft Road) |
2026-2029 |
Completed Milestones
Activity | Completion Date |
---|---|
Transportation Planning Report (TPR) | July 2009 |
Environmental Categorical Exclusion (CE) | March 2010 |
TDOT Funding | April 2010 |
Business Owners Meeting 1 | January 31, 2012 |
Public Meeting 1 | March 8, 2012 |
Public Meeting 2 | April 19, 2012 |
Business Owners Meeting 2 | May 22, 2012 |
Public Meeting 3 | July 26, 2012 |
Construction - Brooks Road Intersection | January 2013 - July 2013 |
Public Meeting 4 | February 21, 2013 |
Public Meeting 5 | May 2, 2013 |
Public Meeting 6 | September 26, 2013 |
Public Meeting 7 | January 29, 2015 |
Right-of-Way Acquisition - Elvis Presley North (Winchester Road to Brooks Road) |
Summer 2018 |
Construction - Elvis Presley North (Winchester Road to Brooks Road) |
May 2021 |