Project Schedule (Updated September 2025)
| Activity | Date | 
|---|---|
| Construction - Middle Segment (Craft Road to Winchester Road)  | 
												2025-2027 (Active)  | 
											
| Right-of-Way Acquisition - South Segment (Shelby Drive to Craft Road)  | 
												2026-2027 (Planned)  | 
											
| Construction - South Segment (Shelby Drive to Craft Road)  | 
												2027-2030 (Planned)  | 
											
Completed Milestones
| Activity | Completion Date | 
|---|---|
| Right-of-Way Acquisition - Elvis Presley Middle (Craft Road to Winchester Road)  | 
												November 2020 - December 2023 | 
| Environmental Re-Evaluation | July 2022 | 
| Construction - Elvis Presley North (Winchester Road to Brooks Road)  | 
												April 2019 - May 2021 | 
| Right-of-Way Acquisition - Elvis Presley North (Winchester Road to Brooks Road)  | 
												Summer 2014 - Summer 2018 | 
| Environmental Re-Evaluation | July 2018 | 
| Public Meeting 7 | January 29, 2015 | 
| Environmental Re-Evaluation | March 2014 | 
| Public Meeting 6 | September 26, 2013 | 
| Public Meeting 5 | May 2, 2013 | 
| Public Meeting 4 | February 21, 2013 | 
| Construction - Brooks Road Intersection | January 2013 - July 2013 | 
| Public Meeting 3 | July 26, 2012 | 
| Business Owners Meeting 2 | May 22, 2012 | 
| Public Meeting 2 | April 19, 2012 | 
| Public Meeting 1 | March 8, 2012 | 
| Business Owners Meeting 1 | January 31, 2012 | 
| TDOT Funding | April 2010 | 
| Environmental Categorical Exclusion (CE) | March 2010 | 
| Transportation Planning Report (TPR) | July 2009 |