Elvis Presley Boulevard Construction Updates

 

Updated January 17, 2020

 

Current Lane Closures

  • Active work zone on the middle of the road.
  • Two outside lanes are open northbound.
  • Two outside lanes are open southbound.
  • Left turns are restricted throughout project

Completed Phase 2 Construction Activities

  • Removal of existing roadway pavement
  • Installation of storm drainage crossings

Current Phase 2 Construction Activities

  • Landscaping
  • Installation of new roadway base and asphalt

Upcoming Phase 2 Activities

  • Switch to Phase 3 - Mid March (tentative)

Construction Schedule

  • Begin - March 2019
  • Phase 1: Complete
  • Phase 2: Winter 2019 - Spring 2020
  • Phase 3: Spring 2020 - Fall 2020
  • Scheduled Completion - Fall 2020

 

Current Lane Assignments

Click on the Image to View Larger Version

Phase 2 Typical Sections

Please note that all dates are subject to change


 

 