Elvis Presley Boulevard Construction Updates

 

Updated September 23, 2025

 

Current Lane Closures

  • Active work zone on east side of the road.
  • Two lanes are open northbound.
  • Two lanes are open southbound.
  • Left turns are restricted throughout the work area.

Current Phase 1B Construction Activities

  • Working between Winchester Road and Bluebird Road
  • Relocation of utilities
  • Installation of new curb and gutter and sidewalk on east side of roadway
  • Installation of new underground storm drainage on east side of roadway
  • Installation of new driveway connections on east side of roadway

Construction Schedule

  • Begin - April 2025
  • Phase 1A: Complete
  • Phase 1B: September 2025 - November 2025
  • Phase 2: November 2025 - January 2026
  • Phase 3: January 2026 - March 2026
  • Phase 4: March 2026 - April 2026
  • Phase 5: April 2026 - July 2026
  • Phase 6: July 2026 - August 2026
  • Phase 7: August 2026 - October 2026
  • Phase 8: October 2026 - January 2027
  • Scheduled Completion - January 2027

 

Current Lane Assignments

Click on the Image to View Larger Version

Phase 1B Typical Sections

Please note that all dates are subject to change


 

 