Elvis Presley Boulevard Construction Updates

 

Updated April 7, 2026

 

Current Lane Closures

  • Active work zone on east side of the road.
  • Two lanes are open northbound.
  • Two lanes are open southbound.
  • Left turns are restricted throughout the work area.

Phase 2 Construction Activities

  • Removal of existing northbound roadway
  • Installation of storm drainage pipes and inlets
  • Installation of concrete sidewalk and curb and gutter
  • Paving of new northbound travel lanes

Construction Schedule

  • Begin - April 2025
  • Phase 1A: Complete
  • Phase 1B: Complete
  • Phase 1C: Complete
  • Phase 2, 3, 4: March 2026 - January 2027
  • Scheduled Completion - January 2027

 

Current Lane Assignments

Click on the Image to View Larger Version

Phase 1B Typical Sections

Please note that all dates are subject to change


 

 

Construction Gallery - April 2026

Construction Gallery - March 2026

Construction Gallery - February 2026

Construction Gallery - January 2026

Construction Gallery - December 2025

Construction Gallery - November 2025

Construction Gallery - June 2025

Construction Gallery - May 2025