Updated April 23, 2025
Current Lane Closures
- Active work zone on west side of the road.
- Three lanes are open northbound.
- Two lanes are open southbound.
- Left turns are restricted throughout the work area.
Current Phase 1A Construction Activities
- Working between Winchester Road and Bluebird Road
- Installation of temporary asphalt pavement on west side of roadway
Construction Schedule
- Begin - April 2025
- Phase 1A: April 2025 - June 2025
- Phase 1B: June 2025 - August 2025
- Phase 2: August 2025 - October 2025
- Phase 3: October 2025 - December 2025
- Phase 4: December 2025 - January 2026
- Phase 5: January 2026 - May 2026
- Phase 6: May 2026 - July 2026
- Phase 7: July 2026 - October 2026
- Phase 8: October 2026 - January 2027
- Scheduled Completion - January 2027
Current Lane Assignments
Click on the Image to View Larger Version
Please note that all dates are subject to change