Updated February 23, 2026
Current Lane Closures
- Active work zone on east side of the road and center of the road.
- Two lanes are open northbound.
- Two lanes are open southbound.
- Left turns are restricted throughout the work area.
Current Phase 1C Construction Activities
- Removal of medians
- Installation of temporary pavement in the median area
- Utility Relocations
Construction Schedule
- Begin - April 2025
- Phase 1A: Complete
- Phase 1B: Complete
- Phase 1C: February 2026 - March 2026
- Phase 2, 3, 4: March 2026 - January 2027
- Scheduled Completion - January 2027
Current Lane Assignments
Click on the Image to View Larger Version
Please note that all dates are subject to change