
Pavement Resurfacing Week of June 22
6/19/2026
Weather permitting, construction crews will begin pavement repair and resurfacing operations along Elvis Presley Boulevard on Monday, June 22.
Traffic will be reduced to 1 lane in each direction in the vicinity of the work. The resurfacing is planned to be completed within 3-4 days after it begins.

April 2026 Construction Update
4/7/2026
Work on Phase 2 has begun, focusing on construction of the east side of Elvis Presley Boulevard throughout the length of the project corridor.
Construction activities in this phase include the installation of new concrete pipe and storm drainage inlets, new concrete sidewalks and curb and gutter, and asphalt paving of the new northbound traffic lanes.

February 2026 Construction Update
2/23/2026
Work has shifted to the center of the roadway along the south half of the project corridor, with the existing medians in the roadway being removed. These areas will then be temporarily paved and will be used as traffic lanes in future phases.
While this median work is taking place, construction of the eastern curb line and drainage improvements are ongoing.

January 2026 Construction Update
1/15/2026
Utility relocations for Phase 1B have been substantially completed, and work is beginning on the installation of new storm drainage. This will consist of the construction of inlets along the side of the new roadway and the installation of new concrete drainage pipe.

November 2025 Construction Update
11/25/2025
Work on Phase 1B continues, with demolition of existing asphalt and sidewalks completed and relocation of utilities underway.
Once the utilities have been fully relocated underground, the existing poles will be removed and construction of the new storm drainage and roadway elements will begin.

September 2025 Construction Update
9/24/2025
Phase 1A construction is complete, and traffic has been shifted to the Phase 1B configuration. During Phase 1B, both northbound and southbound directions will be llimited to 2 lanes each way. The center turn lane will be eliminated.
Construction planned for Phase 1B consists of the installation of new sidewalk, curb and gutter, underground storm drainage, roadway paving, and utility relocations, all on the east side of the roadway.

June 2025 Construction Update
6/10/2025
Phase 1A construction activities are ongoing. Pavement milling on the existing southbound outermost lane as started, and MLGW crews are working to relocate electrical junction boxes to their final location behind the future sidewalk. Once this relocation is complete, grading and paving of a temporary traffic lane will begin.
Construction progress photos can be found on the Construction Page.

Middle Segment Construction Beginning April 2025
4/7/2025
Construction on the Middle Segment, from Craft Road to Winchester Road, is scheduled to begin in the next two weeks. Expect to see the traffic control signs and barrels being installed soon. VuCon, LLC will be the contractor performing the work.
The first phase of work will be the construction of some temporary pavement on the west side of the road, just south of Winchester Road.