
November 2026 Project Update
11/12/2026
Installation of curb and gutter and retaining walls on the east side of the project is ongoing. Traffic signal foundations for new signals at Craft Road, the Guesthouse, and the Graceland Mansion have been started.

November 2026 Project Update
11/4/2026
Installation of the storm drainage on the east side of the roadway is complete, marking a major milestone for the project. The drainage installation was particularly tricky, with multiple underground utilities in the area all located in roughly the same space.
With all of the underground work completed for this side of the road, work is now proceeding on building retaining walls, curb and gutter, sidewalk, driveway connections, and the final roadway base and pavement.

October 2026 Project Update
10/15/2026
Work continues on the east side of the roadway, with crews currently working on the last segment of the storm drainage system. Over the past month, the construction team has been installing drainage inlets and pipes and working with utility providers to make adjustments as needed.
Once the drainage lines are fully installed, work will begin on installing the new curb and gutter, sidewalk, roadway base, and asphalt pavement. Updated progress photos can be found on the Construction Page.

Pavement Resurfacing Week of June 22
6/19/2026
Weather permitting, construction crews will begin pavement repair and resurfacing operations along Elvis Presley Boulevard on Monday, June 22.
Traffic will be reduced to 1 lane in each direction in the vicinity of the work. The resurfacing is planned to be completed within 3-4 days after it begins.

April 2026 Construction Update
4/7/2026
Work on Phase 2 has begun, focusing on construction of the east side of Elvis Presley Boulevard throughout the length of the project corridor.
Construction activities in this phase include the installation of new concrete pipe and storm drainage inlets, new concrete sidewalks and curb and gutter, and asphalt paving of the new northbound traffic lanes.

February 2026 Construction Update
2/23/2026
Work has shifted to the center of the roadway along the south half of the project corridor, with the existing medians in the roadway being removed. These areas will then be temporarily paved and will be used as traffic lanes in future phases.
While this median work is taking place, construction of the eastern curb line and drainage improvements are ongoing.

January 2026 Construction Update
1/15/2026
Utility relocations for Phase 1B have been substantially completed, and work is beginning on the installation of new storm drainage. This will consist of the construction of inlets along the side of the new roadway and the installation of new concrete drainage pipe.

November 2025 Construction Update
11/25/2025
Work on Phase 1B continues, with demolition of existing asphalt and sidewalks completed and relocation of utilities underway.
Once the utilities have been fully relocated underground, the existing poles will be removed and construction of the new storm drainage and roadway elements will begin.